Q.4 Complete
the below mentioned chart:
Activity
|
Pessimist
|
Most likely
|
optimist
|
PERT
|
Variance
|
A
|
20
|
12
|
10
|
||
B
|
30
|
25
|
18
|
||
C
|
105
|
80
|
56
|
||
D
|
200
|
145
|
85
|
||
E
|
145
|
112
|
89
|
Ans:
In the
given problem PERT and variance need to be calculated:
The
formula for calculating the PERT is
PERT = (te) = (to +4tm
+ tp)/6
The
formula for calculating the Variance is
Variance
= (tv) = (tp - to)2 /6
Where
to = Optimistic or activity duration in best scenario.
tm =
Most likely or activity duration resource
availability and dependencies are as assumed.
tp = Pessimistic or activity duration in worst scenario.
The
solution of the given problem is as below:
Activity
|
Pessimist
|
Most likely
|
optimist
|
PERT
|
Variance
|
A
|
20
|
12
|
10
|
13
|
16.67
|
B
|
30
|
25
|
18
|
24.67
|
24.00
|
C
|
105
|
80
|
56
|
80.17
|
400.17
|
D
|
200
|
145
|
85
|
144.17
|
2204.17
|
E
|
145
|
112
|
89
|
113.67
|
522.67
|